Rewiring a Region Post-Hurricane Sandy

Even today, six years after the storm surges flooded cities, washed up boats and destroyed coastal property, the scars of Superstorm Sandy remain. Some are invisible—the emotional damage wrought by the loss of life and home—but others still can be seen in battered buildings and gouged-out shorelines throughout the Mid-Atlantic and into the Northeast, from New York’s Long Island to North Carolina’s Pamlico Sound.

“It’s hard to believe the recovery efforts have been going (don’t want readers to think we are referring to our particular project here vs. overall recovery efforts in the way of the Sandy recovery program) on for six years, with more work in the pipeline ahead of us,” says Parag Kapadia, vice president of project finance for Kanta Electric, which has been involved in restoration efforts since 2015. “We’ve been involved in a few recovery projects, and we’re hoping to pursue more.”

“We were here when Sandy hit, and we remember the devastation it caused…this is a very fulfilling project to work on, and we’re looking forward to continuing that work.”

The Power to Heal

In March 2015, more than two years after Sandy’s initial landfall, the Federal Emergency Management Agency (FEMA) awarded the New York City Housing Authority (NYCHA) a $3 billion grant aimed at repairs and other recovery efforts for 33 public housing complexes within the city.  

Having spearheaded numerous NYCHA projects over the years, Kanta was tasked with relocating all electrical infrastructure—from transformers  for power distribution to emergency generators for backup support—to safer areas in the complexes.

“These electrical services essentially had to be completely reconfigured,” Kapadia explains. “By relocating them above the floodplain, we’re making sure these complexes aren’t susceptible to future flooding.” 

Much like other restoration projects undertaken in the wake of Sandy, Kanta’s work on behalf of NYCHA hasn’t made a lot of headlines, especially not when compared to some of the company’s more high-profile projects, which include solar photovoltaic installation projects including Brooklyn Army Terminal for the NYC Economic Development Corporation as well as the city’s first wind turbine system at the Brooklyn Navy Yard. The firm has also completed installation of ballfield lighting automation for Yankee Stadium.

Yet this particular project has a special place with employees of Kanta, Kapadia explains: “We were here when Sandy hit, and we remember the devastation it caused,” he says. “This is a very fulfilling project to work on, and we’re looking forward to continuing that work.”

Kanta team finishing off resiliency upgrades for the NYCHA Isaacs Houses, of New York, NY.

No Downtime

For a grander-scale picture of Kanta’s capabilities, look no further than the Bronx Family Criminal Court (BFCC). Located in the heart of New York’s northernmost borough, the 10-story, 775,000-square-foot steel-and-glass behemoth was officially opened in 2007 with a price tag of $275 million—both figures well over the original estimates.

Almost immediately, BFCC was criticized for what many saw as glaring safety concerns. Finally, in 2015, the New York City capital committee set aside an additional $35 million for post-construction repairs and fixes. Kanta was awarded a contract to upgrade the facility’s electrical infrastructure.

Typically, when Kanta tackles a project of that size, the crew will work in piecemeal fashion, shutting off sections in order to phase in new power. But a facility like BFCC presents a conundrum: Because you can’t “shut down” court hearings or sentencings, the project mandated ongoing operations—zero interruptions.

“That was one of the biggest challenges we’ve faced,” Kapadia recalls. “It’s a building that’s literally running 24 hours a day.”

Coordinating with all of BFCC’s stakeholders—from facilities managers to court clerks to the chief of the Bronx Police Department—Kanta not only completed the project with zero downtime; they did it on time and under budget.

The project involved replacing a pair of 4,000-amp service panels, installing a new transformer and a 2,000 kilowatt roof-mounted generator, as well as adding fuel piping for the generator, HVAC infrastructure, and more.

Though one of Kanta’s biggest projects to date, it wasn’t the only one the company was focused on. In the three years it took to finalize BFCC, Kanta completed public works projects on behalf of many of the major NYC and NYS agencies including Department of Environmental Protection (DEP), Dormitory Authority State of New York (DASNY), NYS Office of Mental Health (OMH), Economic Development Corporation (EDC), NYC School Construction Authority (SCA), NYC Department of Design and Construction (DDC), NYC Park and Recreation (DPR), and more.

For Kapadia, the resulting workload has been dizzying—and humbling, given how far the company has come.

Powering Up

It was Parag’s father, Prakash Kapadia, who in 1991 launched Kanta Electric with two vans and a handful of residential clients. A first-generation American from India, the elder Kapadia wore every possible hat for the nascent company: estimator, electrician, accountant, customer-service rep.

As the company’s reputation grew, Kapadia realized that, in order to move into the hyper-competitive world of commercial electrical contracting, joining the International Brotherhood of Electrical Workers—the largest union of its kind in the country—was a must.

“That was a huge milestone for him, both personally and professionally,” Parag Kapadia recalls.

Over time, Kanta found a comfortable niche in the public sector, conducting projects on behalf of state and local agencies including the Port Authority, the New York City Economic Development Corporation and the Metropolitan Transportation Authority.

In 2015, Crain’s New York Business magazine included Kanta Electric in its list of the city’s fastest-growing companies. Citing a three-year earnings spike of 314 percent, from $6.9 million in 2011 to $28.6 million in 2014, the honor was sweet vindication.

“It’s a special feeling knowing your work is part of the fabric of New York—that you’re helping make it go,” Kapadia says. “It’s his vision that has brought the company to where it is today, and we’re excited to see what the next 25 years have in store.”